OpenProject is the leading open source project management software.
You can not select more than 25 topics Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
openproject/docs/user-guide/gantt-chart/scheduling/README.md

63 lines
4.5 KiB

---
sidebar_navigation:
title: Automatic and manual scheduling
priority: 999
description: Use manual or automatic scheduling mode in OpenProject
robots: index, follow
keywords: Gantt chart, automatic scheduling, manual scheduling, start date, finish date, relations
---
# Automatic and manual scheduling mode
<div class="glossary">
To schedule work packages in the Gantt chart there is an **automatic scheduling mode (default)** and a **manual scheduling mode** (new in [release 11.0](../../../release-notes/11-0-0)). To add dependencies between work packages you can set them as predecessor or follower in the Gantt chart. The automatic and manual scheduling modes influence the work packages' behaviour when changing dates of other related work packages.</div>
Expanding documentation (#9091) * changed screenshots for projects chapter * changed screenshots in gantt chart chapter * moved "aggregation by project" from work packages to Gantt chart chapter * changed some links * move reference to Excel sync out of Gantt chart chapter * small changes * add initial setup section for administrators to documentation Idea and main content from @ivangriggs Co-Authored-By: ivangriggs <77022874+ivangriggs@users.noreply.github.com> * smaller improvements to docs * improve documentation of manual and automatic scheduling mode * small improvements in docs * small changes * adding section for search options in OpenProject * move section about hourly rate defintion to system admin guide * formatting changes * explaining assignee filter options * change section header to make it detectable when searching for "projects overview" * clean up table of contents, make titles consistent, remove excessive space characters, etc. * update screenshots * changes to project overview docs * add screenshot for search bar * make info about aggregation of changes in activity and notifications easier detectable * small improvements * add info about non member and anonymous role * changes/additions * small changes * add additional options to access context menu * add sum feature for work package list to docs and change screenshot * add/improve info about email notifications * link fixes (necessary due to structural changes in documentation) * working in review comments * changes for time tracking activities * change screen shots for wiki - more functions section * change screenshots and improve description for meetings * improve detectability of mention feature * move FAQ in authentication * add how to reset password * improve explanation on how to un-archive projects * mention Mattermost integration * small correction
4 years ago
As the scheduling mode only affects individual work packages you can combine manual scheduling mode (top-down planning) and automatic scheduling mode (bottom-up planning) within the same project.
| Topic | Content |
| ------------------------------------------------------- | ------------------------------------------------------------ |
| [Automatic scheduling mode](#automatic-scheduling-mode) | What happens to work packages, when you connect them in automatic scheduling mode? |
| [Manual scheduling mode](#manual-scheduling-mode) | What happens to work packages, when you connect them in manual scheduling mode? |
| [Changing modes](#changing-modes) | How can I change between manual and automatic scheduling mode? |
## Automatic scheduling mode
The automatic scheduling mode is generally set as **the default mode** for new work packages. For [dependencies](../#relations-in-the-gantt-chart) between two work packages this means:
- A work package's start date is automatically determined by the start date of its earliest starting child.
- A work package's finish date is automatically determined by the finish date of its latest ending child.
- When you move a work package past the set start date of its follower, the followers start date will be adjusted to its predecessor's finish date. This is not the case the other way round.
Example: Work package 1 ends on October 5th. Its follower work package 2 starts on October 13th. Now work package 1 gets delayed by ten days, you have to adjust the planning. When you set the finish date of work package 1 to October 15th, the start date of work package 2 will automatically be set to October 16th.
Expanding documentation (#9091) * changed screenshots for projects chapter * changed screenshots in gantt chart chapter * moved "aggregation by project" from work packages to Gantt chart chapter * changed some links * move reference to Excel sync out of Gantt chart chapter * small changes * add initial setup section for administrators to documentation Idea and main content from @ivangriggs Co-Authored-By: ivangriggs <77022874+ivangriggs@users.noreply.github.com> * smaller improvements to docs * improve documentation of manual and automatic scheduling mode * small improvements in docs * small changes * adding section for search options in OpenProject * move section about hourly rate defintion to system admin guide * formatting changes * explaining assignee filter options * change section header to make it detectable when searching for "projects overview" * clean up table of contents, make titles consistent, remove excessive space characters, etc. * update screenshots * changes to project overview docs * add screenshot for search bar * make info about aggregation of changes in activity and notifications easier detectable * small improvements * add info about non member and anonymous role * changes/additions * small changes * add additional options to access context menu * add sum feature for work package list to docs and change screenshot * add/improve info about email notifications * link fixes (necessary due to structural changes in documentation) * working in review comments * changes for time tracking activities * change screen shots for wiki - more functions section * change screenshots and improve description for meetings * improve detectability of mention feature * move FAQ in authentication * add how to reset password * improve explanation on how to un-archive projects * mention Mattermost integration * small correction
4 years ago
- You can't change the dates of a work package with children (if it is in automatic scheduling mode).
## Manual scheduling mode
Expanding documentation (#9091) * changed screenshots for projects chapter * changed screenshots in gantt chart chapter * moved "aggregation by project" from work packages to Gantt chart chapter * changed some links * move reference to Excel sync out of Gantt chart chapter * small changes * add initial setup section for administrators to documentation Idea and main content from @ivangriggs Co-Authored-By: ivangriggs <77022874+ivangriggs@users.noreply.github.com> * smaller improvements to docs * improve documentation of manual and automatic scheduling mode * small improvements in docs * small changes * adding section for search options in OpenProject * move section about hourly rate defintion to system admin guide * formatting changes * explaining assignee filter options * change section header to make it detectable when searching for "projects overview" * clean up table of contents, make titles consistent, remove excessive space characters, etc. * update screenshots * changes to project overview docs * add screenshot for search bar * make info about aggregation of changes in activity and notifications easier detectable * small improvements * add info about non member and anonymous role * changes/additions * small changes * add additional options to access context menu * add sum feature for work package list to docs and change screenshot * add/improve info about email notifications * link fixes (necessary due to structural changes in documentation) * working in review comments * changes for time tracking activities * change screen shots for wiki - more functions section * change screenshots and improve description for meetings * improve detectability of mention feature * move FAQ in authentication * add how to reset password * improve explanation on how to un-archive projects * mention Mattermost integration * small correction
4 years ago
The manual scheduling mode is **mostly used when creating a top-down project plan** (e.g. by defining the main phases first). You can then add child work packages without affecting the original (high-level) project schedule.
Changing to the **manual scheduling mode makes sense if**
Expanding documentation (#9091) * changed screenshots for projects chapter * changed screenshots in gantt chart chapter * moved "aggregation by project" from work packages to Gantt chart chapter * changed some links * move reference to Excel sync out of Gantt chart chapter * small changes * add initial setup section for administrators to documentation Idea and main content from @ivangriggs Co-Authored-By: ivangriggs <77022874+ivangriggs@users.noreply.github.com> * smaller improvements to docs * improve documentation of manual and automatic scheduling mode * small improvements in docs * small changes * adding section for search options in OpenProject * move section about hourly rate defintion to system admin guide * formatting changes * explaining assignee filter options * change section header to make it detectable when searching for "projects overview" * clean up table of contents, make titles consistent, remove excessive space characters, etc. * update screenshots * changes to project overview docs * add screenshot for search bar * make info about aggregation of changes in activity and notifications easier detectable * small improvements * add info about non member and anonymous role * changes/additions * small changes * add additional options to access context menu * add sum feature for work package list to docs and change screenshot * add/improve info about email notifications * link fixes (necessary due to structural changes in documentation) * working in review comments * changes for time tracking activities * change screen shots for wiki - more functions section * change screenshots and improve description for meetings * improve detectability of mention feature * move FAQ in authentication * add how to reset password * improve explanation on how to un-archive projects * mention Mattermost integration * small correction
4 years ago
- you want to plan your project top-down without knowing all tasks yet, or
- you want to set a parent work package’s date independently from the dates of its children, or
- you don't want a parent work package's dates being updated automatically when changing the children's dates, or
- you don't want a follower's start date be automatically updated when you change the predecessor's finish date
Expanding documentation (#9091) * changed screenshots for projects chapter * changed screenshots in gantt chart chapter * moved "aggregation by project" from work packages to Gantt chart chapter * changed some links * move reference to Excel sync out of Gantt chart chapter * small changes * add initial setup section for administrators to documentation Idea and main content from @ivangriggs Co-Authored-By: ivangriggs <77022874+ivangriggs@users.noreply.github.com> * smaller improvements to docs * improve documentation of manual and automatic scheduling mode * small improvements in docs * small changes * adding section for search options in OpenProject * move section about hourly rate defintion to system admin guide * formatting changes * explaining assignee filter options * change section header to make it detectable when searching for "projects overview" * clean up table of contents, make titles consistent, remove excessive space characters, etc. * update screenshots * changes to project overview docs * add screenshot for search bar * make info about aggregation of changes in activity and notifications easier detectable * small improvements * add info about non member and anonymous role * changes/additions * small changes * add additional options to access context menu * add sum feature for work package list to docs and change screenshot * add/improve info about email notifications * link fixes (necessary due to structural changes in documentation) * working in review comments * changes for time tracking activities * change screen shots for wiki - more functions section * change screenshots and improve description for meetings * improve detectability of mention feature * move FAQ in authentication * add how to reset password * improve explanation on how to un-archive projects * mention Mattermost integration * small correction
4 years ago
Moving a child work package in the manual scheduling mode will not move the dates of the parent work package. The scheduling differences will be indicated by a black or red bracket underneath (e.g. when a child is shorter or longer than the parent phase). See [this explanation](../#understanding-the-colors-and-lines-in-the-gantt-chart) to find out more about the lines and colors in the Gantt chart.
<video src="https://openproject-docs.s3.eu-central-1.amazonaws.com/videos/OpenProject-Top-down-Scheduling.mp4" type="video/mp4" controls="" style="width:100%"></video>
## Changing mode
Expanding documentation (#9091) * changed screenshots for projects chapter * changed screenshots in gantt chart chapter * moved "aggregation by project" from work packages to Gantt chart chapter * changed some links * move reference to Excel sync out of Gantt chart chapter * small changes * add initial setup section for administrators to documentation Idea and main content from @ivangriggs Co-Authored-By: ivangriggs <77022874+ivangriggs@users.noreply.github.com> * smaller improvements to docs * improve documentation of manual and automatic scheduling mode * small improvements in docs * small changes * adding section for search options in OpenProject * move section about hourly rate defintion to system admin guide * formatting changes * explaining assignee filter options * change section header to make it detectable when searching for "projects overview" * clean up table of contents, make titles consistent, remove excessive space characters, etc. * update screenshots * changes to project overview docs * add screenshot for search bar * make info about aggregation of changes in activity and notifications easier detectable * small improvements * add info about non member and anonymous role * changes/additions * small changes * add additional options to access context menu * add sum feature for work package list to docs and change screenshot * add/improve info about email notifications * link fixes (necessary due to structural changes in documentation) * working in review comments * changes for time tracking activities * change screen shots for wiki - more functions section * change screenshots and improve description for meetings * improve detectability of mention feature * move FAQ in authentication * add how to reset password * improve explanation on how to un-archive projects * mention Mattermost integration * small correction
4 years ago
You can **activate the manual scheduling mode** by clicking on the date of a work package and selecting the box next to "Manual scheduling". This will activate the manual scheduling mode only for the respective work package.
![image-20200929160916841](image-20200929160916841.png)
The pin symbol next to the date indicates that a work package is in manual scheduling mode.
![image-20200929161237109](image-20200929161237109.png)
Changing back to automatic scheduling mode works the same way. Please note: When switching from manual scheduling to automatic scheduling some work packages' dates might be updated according to principles [stated above](#automatic-scheduling-mode).