@ -59,11 +59,11 @@ The **spent unit costs** as well as the total amount of **overall costs** are di
To display and edit the logged costs to a work package, navigate to the work package details view. Here, the total amount of spent costs are displayed. Click on the sum of logged costs on a work package to display the details.
![Edit-logged-costs](Edit-logged-costs.png)
![Edit logged costs](Edit-logged-costs.png)
The detailed logs are displayed in a cost report. To edit a cost entry, click on the Edit icon with the little pen next to a cost entry.
It will open the details view of the cost entry and you will be able to make your changes just as for [Logging costs to a work package](#logging-costs-to-a-work-package).
@ -71,7 +71,7 @@ In some cases, you might want to change the costs manually so that it differs fr
In this case, click on the **Edit icon**, the little pen, next to the cost entry. Now you can manually enter the costs.
![Edit-costs-details](Edit-costs-details.png)
![Edit costs details](Edit-costs-details.png)
Do not forget to **save** your changes.
@ -79,4 +79,4 @@ Do not forget to **save** your changes.
If you made a mistake and need to delete logged costs, click on the **delete icon** next to a cost entry in the cost report.