@ -77,14 +77,14 @@ Feature: Timeline view with filter tests |
|
|
|
|
@javascript |
|
|
|
|
Scenario: The timeline w/o filters renders properly |
|
|
|
|
Given there are the following work packages in project "Space Pilot 3000": |
|
|
|
|
| Subject | Start date | Due date | type | parent | |
|
|
|
|
| Hubert Farnsworth's Birthday | 2841-04-09 | 2841-04-09 | Milestone | | |
|
|
|
|
| Space Pilot | 3000-01-01 | 3000-01-05 | Phase | | |
|
|
|
|
| Mission to the moon | 3000-01-02 | 3000-01-02 | Milestone | Space Pilot | |
|
|
|
|
| Subject | Start date | Due date | type | parent | |
|
|
|
|
| Hubert Farnsworth's Birthday | 2841-04-09 | 2841-04-09 | Milestone | | |
|
|
|
|
| Unrelated | 3000-01-01 | 3000-01-05 | Phase | | |
|
|
|
|
| Mission to the moon | 3000-01-02 | 3000-01-02 | Milestone | Unrelated | |
|
|
|
|
And I am working in the timeline "Storyboard" of the project called "Space Pilot 3000" |
|
|
|
|
When I go to the page of the timeline of the project called "Space Pilot 3000" |
|
|
|
|
And I show only work packages which have the type "Milestone" |
|
|
|
|
And I wait for timeline to load table |
|
|
|
|
Then I should see the work package "Hubert Farnsworth's Birthday" in the timeline |
|
|
|
|
And I should see the work package "Mission to the moon" in the timeline |
|
|
|
|
And I should not see the work package "Space Pilot" in the timeline |
|
|
|
|
And I should not see the work package "Unrelated" in the timeline |
|
|
|
|