openproject/docs/use-cases/resource-management
Maya Berdygylyjova fdfd4f2b89 Fixing a typo 2 years ago
..
README.md Fixing a typo 2 years ago
configure_wp_view.png task(docs): publish use cases (#11983) 2 years ago
openproject_configure_view.png task(docs): publish use cases (#11983) 2 years ago
openproject_display_sums.png task(docs): publish use cases (#11983) 2 years ago
openproject_global_wp_view.png task(docs): publish use cases (#11983) 2 years ago
openproject_save_wp_adjusted_view.png task(docs): publish use cases (#11983) 2 years ago
openproject_sort_by_assignee.png task(docs): publish use cases (#11983) 2 years ago
openproject_work_packages_sum.png task(docs): publish use cases (#11983) 2 years ago
openproject_wp_gantt_view.png task(docs): publish use cases (#11983) 2 years ago
work_package_private_filter.png task(docs): publish use cases (#11983) 2 years ago

README.md

sidebar_navigation description keywords
[{title Resource Management} {priority 990}] Step-by-step instruction about resource management use-case, resource management

Use Case: Resource management

Note: OpenProject does not have the automated functionality to provide detailed resource management or employee work capacity calculations. However, there is a workaround that you can use to configure a visual estimate of task distribution and plan accordingly.

Work packages view

These are the steps you can follow to adjust a work package overview to suit your goals.

resource management

Step 1: Select a project and go to the work package overview by clicking Work packages in the project menu on the left. If you would like to create an overview over multiple projects, select the respective projects and/or subprojects in the Include projects menu between the + Create and the Filter buttons.

Alternatively, you can also chose the Global work package overview by selecting the Waffle icon in the top right corner:

OpenProject global work packages overview

Step 2: You can add existing fields, such as Estimated time, Spent time and Remaining hours to your work packages list. Also, you can create additional custom fields, e.g. Scope (h), to get an overview of the team capacity.

Step 3: You can add these fields via the Insert columns option via the drop-down menu.

Step 4: You can add any filters necessary and sort or group the work packages by assignee.

OpenProject sort work packages by assignee

Step 5: Save your adjusted view by clicking on the Save icon on the left (you can name this view before saving or re-name it later). Save adjusted openrpoject workpage view

This view will be saved and shown under your private work package filters (you can make it public and share with other team members).

OpenProjec work package private filter

Adding sums to the work packages view

You can also use the sum function. Select [⋮] -> Configure view -> Display settings -> and check the Display Sums box:

OpenProject work package configure view

OpenProject display sums

You will see the estimated, spent and remaining hours summed up by user, as well as the overall sum.

OpenProject work packages sums

Gantt chart view

You could also add the Gantt view to add an additional dimension to your overview.

OpenProject work packages Gantt view

This will provide a rough overview of the various tasks assigned to a specific person or team. Adding the Gantt view provides a supplementary overview of when these tasks are scheduled. It is a visual way of looking at approximately how many tasks are assigned to an individual. This view gives you an estimate about the timeline, allowing for adjustments in assignments and timing to be made to balance your resources.

To get a more in-depth overview about who does which tasks and when, you can also switch to the team planner view.