OpenProject is the leading open source project management software.
You can not select more than 25 topics Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
 
 
 
 
 
 
openproject/docs/system-admin-guide/time-and-costs
ML-OpenP 5d4bba9801
Expanding documentation (#9091)
4 years ago
..
README.md Expanding documentation (#9091) 4 years ago
Sys-admin-budgets-cost-types-list-1579853898118.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
Sys-admin-budgets-cost-types-list.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
Sys-admin-budgets-cost-types.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
Sys-admin-budgets-create-cost-types.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
Sys-admin-configure-costs.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
System-admin-guide-budgets.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
System-admin-guide-cost-types.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago
image-20201006155423521.png renaming of 'budgets' to 'time and costs' in system admin docs 4 years ago

README.md

sidebar_navigation description robots keywords
[{title Time and costs} {priority 680}] Define cost types and change the currency in OpenProject. index, follow cost type, currency, time and costs, budget

Time and costs

You can configure costs in OpenProject and create cost types to track unit costs. Also, you can configure the currency you want to use for your cost reports.

Navigate to Administration -> Time and costs.

Settings

Navigate to Administration -> Time and costs -> Settings to define settings for costs in OpenProject.

  1. Configure the currency used in the system, e.g. EUR.
  2. Specify the format of the currency, if the number should be before or after the currency, e.g. 10 EUR, or $ 10.
  3. Press the blue Apply button to save your changes.

image-20201006155423521

Create and manage cost types

You can create and manage cost types to book unit costs to work packages in OpenProject.

Navigate to -> Administration -> Time and costs -> Cost types to create and manage unit costs types.

Click the green + Cost type button to create a new cost type.

You can set the following options:

  1. Enter a name for the cost type.
  2. Define the unit name for this cost type, e.g. Euro, piece, day, etc.
  3. Set the pluralized unit name, e.g. Euros, pieces, days, etc.
  4. Choose if the cost type should be the default cost type when booking new unit costs.
  5. Define the Rate history and set a date from which this cost type should be valid and set a rate (in the specified unit) for this date.
  6. With the + icon you can add additional rates for other dates.
  7. The delete icon will remove a rate for a certain date.
  8. Do not forget to save your changes.

Sys-admin-budgets-cost-types

In the overview list of all cost types you can define the following.

  1. Filter for cost types at a certain fixed date in the list
  2. Choose whether also locked cost types should be displayed
  3. Press the blue apply button: This way you will get the cost types with the rate (at the chosen fixed date) displayed in the list below.
  4. Click on the name of a cost type to edit an existing cost type.
  5. Set a current rate (for the current valid from period) and press the save icon to apply it.
  6. Lock a cost type. Please note that you can only lock but not delete cost types.

Sys-admin-budgets-cost-types-list

**Note**: With cost types you can also book any kind of units to work packages, e.g. vacation days, leaves, travel days, etc.. Just choose 1 as a unit. This way, you could e.g. track vacation days against a vacation budget and evaluate the days in the [cost reporting](../../user-guide/time-and-costs/reporting/).