OpenProject is the leading open source project management software.
You can not select more than 25 topics Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
 
 
 
 
 
 
openproject/docs/user-guide/work-packages/set-change-dates
Christophe Bliard a5335a992b
Remove documentation about unsupported feature
2 years ago
..
README.md Remove documentation about unsupported feature 2 years ago
banner-automatically-scheduled.png Added duration and non-working days 2 years ago
banner-dates-limited.png Added duration and non-working days 2 years ago
banner-manual-relations-ignored.png Added duration and non-working days 2 years ago
banner-other-workpackages-affected.png Added duration and non-working days 2 years ago
banner-show-relations-button.png Added duration and non-working days 2 years ago
clear-date-field.png Added duration and non-working days 2 years ago
datepicker-3-days.png Updated date picker screenshots 2 years ago
datepicker-5-days.png Updated date picker screenshots 2 years ago
duration-field-focus.png Added info on duration to other page 2 years ago
manual-scheduling-switch.png Added duration and non-working days 2 years ago
milestone-datepicker.png Added duration and non-working days 2 years ago
one-day-event.png Added duration and non-working days 2 years ago
standard-date-picker-legend.png Added duration and non-working days 2 years ago
standard-date-picker.png feat(doc-images): reduce png file sizes 2 years ago
successful-update.png Fixed image sizes manually (#11104) 2 years ago
working-days-only-switch.png Added info on duration to other page 2 years ago

README.md

sidebar_navigation description keywords
[{title Set and change dates and duration} {priority 890}] How to use the date picker to set and update the start date, finish date and duration of a work packages date picker start finish dates duration change modify update relations work package

Set and change dates and duration of work packages

Feature Documentation for
Set start and finish dates How to set start and finish dates, and how to change them
Working days and duration How to set duration, and how it affects start and finish dates
Scheduling mode Enabling manual scheduling and what it does
Information and warning ban ners What the different warning and information banners mean

Set start and finish dates

You can change the start and finish dates of a work package by opening the date picker.

The standard date picker with different elements highlighted

  1. Manual scheduling switch
  2. Working days only switch
  3. Start date, finish date and duration input fields
  4. Mini calendars for date range preview
  5. Save and cancel buttons

You can open the date picker for a work package from a number of different places:

Using the date picker

You can enter dates either by typing them in into the start and finish date fields or by clicking on individual dates in the mini calendar below.

Note: Typed dates need to be in the standard ISO 8601 format: YYYY-MM-DD (so 12 October 2022 would be 2022-10-12).

They will nevertheless be displayed in your desired format (usually depending by your region or language).

You can also click on the Today link below the start and finish date fields to use today's date.

A more intuitive way to select start and end dates is to simply click on two different dates in the mini calendars below. Two calendar months are displayed for better visibility.

Start by clicking on a start date. This will enter the selected date as the start date, mark it with a dark color on the mini calendar below and move the focus to the finish date field. Hovering on different finish dates will give you a preview of the date range for the work packakge if you click this second date. Once you have decided on a finish date, click on it. This will enter the finish date in the date field and mark that date with another dark color. The dates in between will be highlighted with a lighter colour.

To confirm the selected dates, click on the Save button. The green message on top of the work package indicates a successful update.

A green toast indicating successful update

To clear a date field, simply click on the clear icon ("×") icon when the field is in focus.

A focused date field has an X to clear it

Date changes are documented in the work package Activity.

Advanced functionality

  • The date picker allows you to pick start and finish dates in the opposite order. Clicking on a start date and then moving backwards to click on an earlier date will then use that first date as the finish date and the second (earlier) date as the start date.

  • Once you have selected your start and finish dates, you can adjust either field without resetting the other one by clicking on a new date near the previously selected date. This, however, depends on which date field is in focus. For example, clicking on a new start date that is 2 days earlier when the start date field is in focus simply replaces the original start date (conserving the finish date). However, clicking on that same date when the finish date field is in focus clears the finish date and uses the clicked date as the new start date. A second click then allows to select the new finish date. This should feel quite intuitive when you use it.

One-day events

If you want the work package to start and finish on the same date, simply click the same date twice.

Date picker with the same start and finish dates

Work packages with only a start date or only a finish date are automatically considered one-day events.

Certain work package types (such as Milestones) can only span one day and thus have only one date field:

Milestones have datpickers with a single date field

Working days and duration

Starting with OpenProject 12.3, it is possible to manually input a duration for a work package and decide whether this duration should include working days only or all calendar days.

Note: Working dates are currently defined by the administrator of your OpenProject instance. By default, they are Monday to Friday, with Saturday and Sunday considered non-working. If you are an administrator, please read our admin guide on working days

When upgrading to 12.3 from a previous version: Please note that this switch will be set to off for all existing work packages so as to preserve start and finish dates. However, the switch will be on by default for new work packages.

Working days

The "Working days only" switch on the datepicker

The Working days only switch is on by default, and the date picker skips over the weekend (or the days defined as non-working days) when scheduling work packages and deriving duration. In this mode, non-working days are marked with a darker colour and are not clickable. Work packages cannot start or finish on non-working days, and these days do not count towards the calculation of duration.

Switching Working days only off will turn the previously disabled non-working days into regular working days, and make them available for scheduling. The duration will now take these days into account.

Duration

Duration is always expressed in days, and is the total number of days between the start and finish dates (inclusive). The Duration field is directly related to the start and finish dates, but does not require them. Changing one will change the other.

The Duration field is to the right of the Finish date

Duration can either be automatically derived from dates or entered manually. When the duration field is is focus, you can enter a number corresponding to days; you do you not need to type the word "days" (or the equivalent in your language), this will automatically be added for you.

Duration when start and finish dates exist

When you set a start and a finish date, the duration is automatically derived. For example, if the start date is set to Wednesday, 12 October, 2022 and the finish date to Friday, 14 October, 2022, a duration of 3 days is derived.

A duration of 3 days automatically derived from the start and finish dates

Changing the duration when both start and finish dates are already set will then update the finish date. In our example, if you change the duration to 4 days, one of two things can happen:

  • If the Working days only switch is on, the finish date is automatically set to Monday, 17 October, 2022 (since Saturday and Sunday are not working days)
  • If the Working days only switch is off, the finish date is automatically set to Saturday, 15 October, 2022 (since all calendar days are included)

Changing the start and finish dates will also affect duration. In our example, if you change the start date to Monday, 10 October 2022 without changing the finish date of Friday, 14 October 2022, the duration is automatically updated to 5 days.

A duration of 5 days automatically derived from the start and finish dates

Duration when only one date exists

A work package cannot have only one date and a duration; the other date is automatically derived. This derived date can either be the start date or the finish date.

For example, if you set the start date to Wednesday, 12 October and enter a duration of 3 days, a finish date of Friday, 14 October is automatically derived. Conversely, if you set the finish date Friday, 14 October and then set the duration to 3 days, the date picker will count backwards and derive a start date of Wednesday, 12 October.

Duration without start and finish dates

It is possible for a work package to have only duration without any start or finish dates set.

Note: If you add even one date to a work package with duration, the other date is automatically derived; it is not possible to have just one date (start or finish) and duration set. Please note also that if a work package with only duration derives its start date via a relation, the finish date is then also derived.

Setting only duration without start or finish dates is especially useful when you have a general estimation of how long different tasks or phases of a project will take, but do not have exact dates defined quite yet.

Pro tip: This feature makes it possible to automatically derive an estimated start or finish date for entire project.

To do so, create a series of work packages that represent the main phases and set the approximate duration for each. Link them all using follow/precedes relationships. Now, when you set a start date on the first work package in the series, the start and end dates for all other work packages will be derived.

Scheduling mode

Manual scheduling

A switch on the date picker allows you to enable manual scheduling

Switching "Manual scheduling" on enables manual scheduling mode for the work package. This ignores work package relations such that you're able to select any start and end dates, even ones that would normally be restricted due to follows/proceeds relationships.

Manual scheduling also decouples the start and end dates of parent and children work packages. This means that the dates of parents are no longer constrained by those of the children, and children can be scheduled outside of the range of parent work packages. These relationships are completely ignored as far as scheduling is concerned, but are not removed (so they will still be visible in Gantt view); the constraints are respected again if you switch manual scheduling off.

Manual scheduling can be useful when you need to anchor a work package to fixed dates, for example because the dates of preceding or following work packages are not yet known.

Information and warning banners

OpenProject 12.2 introduced helpful banners to give you important contextual information when changing dates on work packages with relations.

Information banners have a blue background and display information that is helpful to the user but is not critical. Warning banners have an orange background and display information that is critical, with potentially larger consequences to project scheduling.

There are four possible banners:

Automatically scheduled

A blue banner informing the user that the worked package is automatically scheduled

This information banner is displayed when the dates of the current work package are derived from existing relations and can therefore not be modified. This is the case of parent work packages whose start and finish dates are derived from the earliest and latest child work packages respectively.

It is nevertheless possible to input specific start and finish dates for such work packages by enabling manual scheduling (which will ignore relations from which the dates were originally derived).

Available start date and finish dates limited by relations.

A blue banner informing the user that certain dates are limited by relations

This information banner is displayed when certain date ranges are disabled due to constraints imposed by follows/precedes relations. For example, a work packages following another one cannot be scheduled before the finish date of the the preceding one.

Manually scheduled, relations ignored

An orange banner warning the user that manual scheduling will ignore existing relations

This warning banner is displayed when you enable manual scheduling on work packages that have follows/precedes or parent/child relations, which are now ignored and no longer limit which dates can be selected for this work package. This also means that changes a manually scheduled work package no longer affect others, despite those existing relations.

This banner is not displayed when manual scheduling is enabled on work packages without relations.

Other work packages affected

An orange banner warning the user that changing these dates will affect other the dates of work packages

This warning banner is displayed on work packages whose start and end dates affect those of other related work packages. For example, when changing the finish date will consequently change the start date of another (following) work package and/or the finish date of a parent.

Info: When both an information and a warning banner are applicable to a work package, only the more important warning banner is displayed.

Show Relations button

The Show Relations button in an information or warning banner

The information and warning banners also feature a Show Relations button. Clicking on this will open a new tab that displays work packages with direct relations to the current work package in Gantt view, in hierarchy mode.

Info: This preview is intended to give a quick overview of only direct relations that might affect scheduling options for the current work package. It does not show second-level relations (and above). To get a full overview, please use the project work package list view or Gantt view with your desired filter/view configuration.