OpenProject is the leading open source project management software.
You can not select more than 25 topics Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
 
 
 
 
 
 
openproject/docs/user-guide/budgets
ML-OpenP bdee8ceeb3
Docs changes 12/2020 for project custom fields, work package custom fields and other improvements (#8871)
4 years ago
..
Budget-assign-work-package.png Move help into docs 5 years ago
Budget-planned-labor-costs.png Move help into docs 5 years ago
Budgets-details-view.png Move help into docs 5 years ago
Budgets-details.png Move help into docs 5 years ago
Budgets-planned-unit-costs.png Move help into docs 5 years ago
Budgets_create-new.png Move help into docs 5 years ago
README.md Docs changes 12/2020 for project custom fields, work package custom fields and other improvements (#8871) 4 years ago
image-20191128163951599.png Move help into docs 5 years ago
image-20191128165511260.png Move help into docs 5 years ago
image-20191128170108630.png Move help into docs 5 years ago

README.md

sidebar_navigation description robots keywords
[{title Budgets} {priority 780}] Find out how to create and manage budgets for a project in OpenProject. index, follow budgets, project budget, costs

Budgets

You can create and manage a project budget in OpenProject to keep track of your available and spent costs in a project.

You can add planned unit costs as well as labor costs for the project.

Then, you will assign work packages to a budgets. If you log time or costs to this work package the costs will booked to this budget and show the percentage spent for a project budget.

Topic Content
Create a project budget How to set up a project budget in OpenProject?
Add planned unit costs How to add planned unit costs to a budget?
Add planned labor costs How to add planned labor costs to a budget?
Assign a work package to a budget How to assign a work package to book time and costs to a project budget?
View details and update budget How to display the details, update, copy or delete a project budget?
Frequently asked questions (FAQ) What are frequent questions regarding budgets?

Create a project budget

In order to create a budget in your project, please activate the Budgets module in the project settings.

To create your first budget in OpenProject, click the green + Budget button on the top right of the page.

Budgets_create-new

In the detailed view you can enter the details for your project budget, add planned unit costs and planned labor costs.

  1. Enter a subject for your budget so you can identify it easily.
  2. Enter a detailed description to add further information to your budget, e.g. budget owner, status and more.
  3. Upload more files to your budgets with drag and drop or by clicking on the field and choosing a file from the explorer.
  4. Enter a fixed date: this date is the basis for the budget to calculate the planned costs based on the configured hourly rate in the user's profile or the cost types. The rates can be configured for different date ranges, therefore, you need to set a fixed date for a budget for which the costs will be calculated.

Budgets-details

Add planned unit costs

You can add planned unit costs to a budget in your project. These unit costs first need to be configured in the system's administration.

  1. Enter the number of units of the cost type to add to your project budgets.

  2. Choose the cost type you would like to plan for your budget from the drop-down list. The cost types first need to be configured in the system administration.

    The unit name will be set automatically according to the configuration of the cost types in your system administration.

  3. Add a comment to specify the unit costs.

  4. The planned costs for this cost type will be calculated automatically based on the configuration of the cost per unit for this cost type. The cost rate will be taken from the fixed date you have configured for your budget. You can click the edit icon (small pen) if you want to manually overwrite the calculated costs for this cost type.

  5. Click the delete icon if you want to drop the planned unit costs.

  6. The + icon will add a new unit cost type for this budget.

Budgets-planned-unit-costs

Add planned labor costs

You can also add planned labor costs to a budget.

  1. Set the hours that will be planned for a user on this budget.
  2. Add a user from the drop-down list.
  3. You can include a comment for your planned labor costs if needed.
  4. The total amount of planned costs will be calculated based on the entered hours and the hourly rate configured for this user in the user profile. You can manually overwrite the calculated planned labor costs by clicking the edit icon (pen) next to the calculated amount. The costs will be calculated based on the hourly rate taken from the fixed date for your budget.
  5. With the delete icon you can remove the planned labor costs from the budget.
  6. Add more planned labor costs for different users to your budget with the + icon.
  7. Save and submit your changes by pressing the blue button.

Budget-planned-labor-costs

Assign a work package to a budget

To add a work package to a project budget to book time and costs to a budget, navigate to the respective work package detailed view.

In the Costs section, select the budget which you want to assign this work package to. You will see a list of budgets configured in your project in the drop-down list.

Now, all time and costs booked to this work package will be booked against the corresponding budget.

Budget-assign-work-package

View details and update budget

You can view the details of a budget and make changes to your budget by selecting it from the list of budgets.

budget-list

Click on the subject to open the details view of the budget.

You will get and overview of planned as well as spent costs and the available costs for your variable rate budget. Also, the total progress of the budget (ratio spent) is displayed. Furthermore the fixed rate is shown from which the costs for labor and unit costs are being calculated.

  1. Update the budget and make changes to e.g. planned unit costs or planned labor costs.
  2. Copy the budget to use it to create a new budget based on the configurations for this budget.
  3. Delete the budget.
  4. In the budget details you will see all planned unit costs.
  5. The work packages assigned to this budget that have actual unit costs booked.
  6. The planned labor costs are displayed for this budget.
  7. The actual labor costs list all work packages that are assigned to this budget and have logged time on it.

Budgets-details-view

**Note**: The costs are calculated based on the [configuration for cost types](../../system-admin-guide) and the [configured hourly rate](../time-and-costs/#define-hourly-rate-for-labor-costs) in the user profile.

Frequently asked questions (FAQ)

How do I prepare a budget in OpenProject?

Budgets are currently limited to a single project. They cannot be shared across multiple projects. This means that you would have to set up a separate budget for the different main and sub projects. You can however use cost reports to analyze the time (and cost) spent across multiple projects. For details, you can take a look at our time and cost reports user guide.