#-- copyright
# OpenProject Costs Plugin
#
# Copyright (C) 2009 - 2014 the OpenProject Foundation (OPF)
#
# This program is free software; you can redistribute it and/or
# modify it under the terms of the GNU General Public License
# version 3.
#
# This program is distributed in the hope that it will be useful,
# but WITHOUT ANY WARRANTY; without even the implied warranty of
# MERCHANTABILITY or FITNESS FOR A PARTICULAR PURPOSE. See the
# GNU General Public License for more details.
#
# You should have received a copy of the GNU General Public License
# along with this program; if not, write to the Free Software
# Foundation, Inc., 51 Franklin Street, Fifth Floor, Boston, MA 02110-1301, USA.
#++
Feature: Permission View Own hourly and cost rates
@javascript
Scenario: Users that by set permission are only allowed to see their own rates, can not see the rates of others.
Given there is a standard cost control project named "Standard Project"
And the role "Supplier" may have the following rights:
| view_own_hourly_rate |
| view_work_packages |
| view_work_packages |
| view_own_time_entries |
| view_own_cost_entries |
| view_cost_rates |
| log_costs |
And there is 1 User with:
| Login | testuser |
| Firstname | Bob |
| Lastname | Bobbit |
| default rate | 10.00 |
And the user "testuser" is a "Supplier" in the project "Standard Project"
And the project "Standard Project" has 1 issue with the following:
| subject | test_work_package |
And the issue "test_work_package" has 1 time entry with the following:
| hours | 1.00 |
| user | testuser |
And there is 1 cost type with the following:
| name | Translation |
| cost rate | 7.00 |
And the work package "test_work_package" has 1 cost entry with the following:
| units | 2.00 |
| user | testuser |
| cost type | Translation |
And the user "manager" has:
| hourly rate | 11.00 |
And the issue "test_work_package" has 1 time entry with the following:
| hours | 3.00 |
| user | manager |
And the work package "test_work_package" has 1 cost entry with the following:
| units | 5.00 |
| user | manager |
| cost type | Translation |
And I am already logged in as "testuser"
When I am on the page for the issue "test_work_package"
Then I should see "1 hour"
And I should see "2 Translations"
And I should see "24.00 EUR"
And I should not see "33.00 EUR" # labour costs only of Manager
And I should not see "35.00 EUR" # material costs only of Manager
And I should not see "43.00 EUR" # labour costs of me and Manager
And I should not see "49.00 EUR" # material costs of me and Manager
When I am on the work_packages page for the project called "Standard Project"
# ensure the page is loaded before opening the columns dropdown. Otherwise
# there will be no columns to choose from.
And I should see "status" within ".work-package-table--container"
And I choose "Columns" from the toolbar "settings" dropdown
And I select to see columns
| Overall costs |
| Labor costs |
| Unit costs |
And I click "Apply"
Then I should see "EUR 24.00"
And I should see "EUR 10.00"
And I should see "EUR 14.00"
And I should not see "EUR 33.00" # labour costs only of Manager
And I should not see "EUR 35.00" # material costs only of Manager
And I should not see "EUR 43.00" # labour costs of me and Manager