OpenProject is the leading open source project management software.
You can not select more than 25 topics Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
 
 
 
 
 
 
openproject/docs/user-guide/gantt-chart
ML-OpenP af89682516 Many words corrected to lower case 4 years ago
..
scheduling Many words corrected to lower case 4 years ago
Gantt-chart-autozoom.png Move help into docs 5 years ago
Gantt-chart-zoom.png Move help into docs 5 years ago
README.md Documentation: spelling, smart characters, invalid links fixed (#8940) 4 years ago
activate-gantt.gif Move help into docs 5 years ago
configure-gantt-chart.gif Move help into docs 5 years ago
create-new-element-gantt-chart.gif Move help into docs 5 years ago
dependencies-gantt-chart-1566556144225.gif Move help into docs 5 years ago
image-20201007164653327.png Gantt chart, System settings, Copy projects 4 years ago
print-gantt-chart.gif Move help into docs 5 years ago

README.md

sidebar_navigation description robots keywords
[{title Gantt charts} {priority 865}] Create project timelines with Gantt charts in OpenProject index, follow gantt chart, timeline, project plan, gantchart

Gantt charts

The **Gantt chart** in OpenProject displays the work packages in a timeline. You can collaboratively create and manage your project plan. Have your project timelines available for all team members and share up-to-date information with stakeholders. You can add start and finish dates and adapt it with drag and drop in the Gantt chart. Also, you can add dependencies, predecessor or follower within the Gantt chart.
Topic Content
Activate the Gantt chart How to activate the Gantt chart in OpenProject?
Create a new element How to add a new item to the Gantt chart?
Relations in the Gantt chart Create and display dependencies in the Gantt chart.
Understanding the colours and lines in the Gantt chart What do the clamps, lines and symbols in the Gantt chart mean?
Gantt chart configuration How to configure the view of your Gantt chart, e.g. add labels?
Synchronize data between OpenProject and Excel How to synchronize data from OpenProject to Excel?
Gantt chart views How to zoom in and out and activate the Zen mode?

Activate the Gantt chart

A Gantt chart can be activated in any work package list, to display the work packages in a timeline view.

To activate the Gantt chart, select the Gantt icon at the top right of the work package list.

activate-gantt

Create a new element in the Gantt chart

To add a work package (e.g. phase, milestone or task) to a Gantt chart, click the + Create new work package link at the bottom of the work package list view.

You can add a subject and make changes to type, status or more fields.

In the Gantt chart you can schedule the work package with drag and drop and change the duration.

To change the order of an item in the Gantt chart, click the drag and drop icon (6 dots) at the left hand side of the work package row. Drag the item to the new position. The blue horizontal line indicates the new position to drop the element.

create-new-element-gantt-chart

How to change the duration of an element in the Gantt chart?

To change the duration of a work package in the Gantt chart view, hover over the work package in the Gantt chart and use the little arrows on its ends to adjust the start date or finish date. This will shorten or prolong its duration. To move a work package on the time line just click on it and drag and drop it to the desired point of time. This will change its start and finish date.

Relations in the Gantt chart

In the Gantt chart you can track dependencies of work packages (e.g. phases, milestones, tasks). This way you can get an easy overview of what needs to be done in which order, e.g. what tasks need to be completed to achieve a milestone.

To add a dependency right-click on an element in the Gantt chart.

In the menu, choose Add predecessor or Add follower.

Select the item to which you want to create a dependency. The precede and follow relation is marked with a small blue line in the Gantt chart.

dependencies-gantt-chart

OpenProject does not yet include a baseline feature to compare scheduled versions. However, we are aware of the need for it and documented it. Please check here https://community.openproject.com/projects/openproject/work_packages/26448/activity for an update.

To find out about how work packages behave, when you move their predecessor or follower or change the date of a child work package please read our guide for the Automatic and manual scheduling mode.

Understanding the colours and lines in the Gantt chart

  • A blue line connects two work packages, they are predecessor and follower.
  • The vertical red dotted line indicates today's date.
  • A black clamp indicates the duration from the start date of a work packages earliest starting child until the end date of a work packages latest ending child.
  • A red clamp indicates the same as the black clamp, with an important difference: The clamp turns red if the dates derived from the children are before or after the manually scheduled dates (of this parent work package). The clambs are black in case the derived dates are within the set dates (of this parent).
  • A diamond symbol stands for a milestone.
  • A bar stands for work packages like phases and tasks.

Gantt chart configuration

To open the Gantt chart configuration, please open the settings icon with the three dots on the upper right of the work package module. Choose Configure view ... and select the tab Gantt chart.

Here you can adapt the Zoom level, or choose Auto zoom which will select a Zoom level which best fits to your browser size to have optimal results on a page.

Also, you have Label Configuration for your Gantt chart. You can add up to three additional labels within the chart: On the left, on the right and on the far right. Just select which additional information you would need to have in the Gantt chart. This can be especially relevant if you want to print your Gantt chart.

Click the Apply button to save your changes.

configure-gantt-chart

How to export data from a Gantt diagram?

To export the data from your Gantt chart there are several possibilities:

How to print a Gantt chart?

The Gantt chart can be printed via the browser's printing function. It is optimized for Chrome.

First, make sure to add the labels you will need in the Gantt chart, e.g. Start date, Finish date, Subject, in the Gantt chart configuration.

Choose the Auto zoom by clicking on the Auto zoom button on top of the Gantt chart.

Optimize the screen by dragging the Gantt chart to the far left so that only the Gantt chart is seen.

Then, press CTRL + P to print the Gantt chart view.

Make sure you select Landscape as a print layout.

In the settings, enable the Background graphics for printing.

Press the Print button.

print-gantt-chart

For other browsers, please simply follow the browser's printing instruction to optimize results.

Synchronize data between OpenProject and Excel

You can synchronize your work package data between OpenProject and Excel (two-way synchronization). By extension you could import MS Project files - by saving them as Excel files and importing them into OpenProject. You can download a free Excel synchronization template to do this.

Follow our [Step by step guide how to synchronize your Excel Sheet with OpenProject](../integrations/Excel Synchronization).

Gantt chart views

Zoom in the Gantt chart

To zoom in and zoom out in the Gantt chart view, click on the button with the + and - icon on top of the chart.

Gantt-chart-zoom

Auto zoom

Select the auto zoom button on top of the Gantt chart to have the best view of your Gantt chart.

Gantt-chart-autozoom

Zen mode

The zen mode gives you more space to focus on the tasks at hand. It's almost like activating the full screen view in your browser. To exit press the Esc key or click on the zen mode symbol again.

image-20201007164653327