kanbanworkflowstimelinescrumrubyroadmapproject-planningproject-managementopenprojectangularissue-trackerifcgantt-chartganttbug-trackerboardsbcf
You can not select more than 25 topics
Topics must start with a letter or number, can include dashes ('-') and can be up to 35 characters long.
86 lines
4.1 KiB
86 lines
4.1 KiB
---
|
|
sidebar_navigation:
|
|
title: Calendar
|
|
priority: 840
|
|
description: Create a calendar in OpenProject.
|
|
robots: index, follow
|
|
keywords: calendar
|
|
---
|
|
|
|
# Calendar
|
|
|
|
The calendar shows all of the project’s work packages in calendar form.
|
|
|
|
| Feature | Documentation for |
|
|
| ------------------------------------------------------------ | ----------------------------------------------------- |
|
|
| [Calendar overview](#calendar-overview) | How to use the calendar in OpenProject. |
|
|
| [Filters in calendar](#filters-in-calendar) | How to filter in the calendar view. |
|
|
| [Zen mode](#zen-mode) | How to work distraction free in a calendar view. |
|
|
| [Project overarching calendar](#project-orverarching-calendar) | How to display more than one project in the calendar. |
|
|
| [FAQ](#frequently-asked-questions-(faq)) | Frequently asked questions |
|
|
|
|
## Calendar overview
|
|
|
|
To display the calendar in a project, the module **Calendar** needs to be activated in the [project settings](../projects/#activate-modules).
|
|
|
|
When you open the calendar, all work packages within the current project are displayed on the calendar, displaying the title of the work package. The colors represent the different [work package types](../../system-admin-guide/#work-package-types).
|
|
|
|
The current month is automatically selected. You can change the date range between month or week and navigate through the views with the arrows on the left. The **today** button brings you back to the current date.
|
|
|
|
Hovering over one item displays more information to a work package, such as the type, status, start and finish date, assignee and priority, as well as the project to which the work package belongs.
|
|
|
|
Click on one item to open the work package details or to edit an item.
|
|
|
|
![calendar](1568639577828.png)
|
|
|
|
## Filters in calendar
|
|
|
|
You can filter the work packages in the calendar view by adding any number of filters, e.g. *Author*, *Due Date*, *Priority*, *Assignee*, etc.
|
|
|
|
Click the **Filter** button on the top right above the calendar to open the filter details.
|
|
|
|
To add another filter criteria, select the drop down next to **+ Add filter** and choose a filter criteria.
|
|
|
|
The number of different filter criteria is displayed on the filter button.
|
|
|
|
![filter-calendar](filter-calendar.png)
|
|
|
|
You can also display the calendar on the dashboard in the [project overview page](#project-overview).
|
|
|
|
## Zen mode
|
|
|
|
You can display the calendar in a full screen view to eliminate header and project menu and work distraction free.
|
|
|
|
Click the **Activate zen mode** button on the top of the calendar.
|
|
|
|
Click Escape (Esc) to leave the Zen mode.
|
|
|
|
![zen-calendar](zen-calendar.png)
|
|
|
|
## Project overarching calendar
|
|
|
|
It is possible to display the work packages from more than one project in the calendar. However, these projects need to be sub-projects of the current project.
|
|
|
|
Open the filter and select subproject as filter criteria.
|
|
|
|
Choose the sub-projects which you also want to display in the calendar view.
|
|
|
|
![subproject-calendar](subproject-calendar.png)
|
|
|
|
It is not possible to add work packages from projects which are not in a project hierarchy.
|
|
|
|
|
|
|
|
## Frequently asked questions (FAQ)
|
|
|
|
### What information can be displayed in the calendar?
|
|
|
|
The calendar automatically displays the start and end dates of work packages in the current project. Additionally, the start and end dates of versions are shown in the calendar.
|
|
|
|
### Where can I embed / activate the calendar?
|
|
|
|
To use the calendar in a project, you need to [activate the “Calendar” module in the project settings](../projects/#activate-modules). Afterwards you can access the calendar in the project menu, as well as add it in the [project overview](#project-overview). You can also enable the calendar in your [“My page” view](#my-page).
|
|
|
|
### Is there an option to export or sync the calendar?
|
|
|
|
It is currently not possible to export or sync the calendar. You can however [export meetings as iCalendar file](#meetings) and import them to your external calendar.
|
|
|