sidebar_navigation:
|
|
title: Work packages introduction
|
|
priority: 700
|
|
description: Introduction to work packages in OpenProject.
|
|
robots: index, follow
|
|
keywords: work packages introduction, attributes, values, task
|
|
---
|
|
|
|
# Introduction to Work Packages
|
|
|
|
In this document you will get a first introduction to work packages. You will find out how to create and update work packages in a project.
|
|
|
|
For further documentation, please visit our [user guide for work packages](../../user-guide/work-packages).
|
|
|
|
| Topic | Content |
|
|
| ------------------------------------------------------------ | --------------------------------------------------------- |
|
|
| [What is a work package?](#what-is-a-work-package) | Find out what a work package in OpenProject is. |
|
|
| [Create a new work package](#create-a-new-work-package) | How to create a new work package in a project? |
|
|
| [Open and edit a work package](#open-and-edit-a-work-package) | How to open and make changes to an existing work package? |
|
|
| [Activity of work packages](#activity-of-work-packages) | See all changes in a work package. |
|
|
|
|
<video src="https://openproject-docs.s3.eu-central-1.amazonaws.com/videos/OpenProject-Work-Packages.mp4" type="video/mp4" controls="" style="width:100%"></video>
|
|
|
|
## What is a work package?
|
|
|
|
A work package in OpenProject can basically be everything you need to keep track off within your projects. It can be e.g. a task, a feature, a bug, a risk, a milestone or a project phase. These different kinds of work packages are called **work package types**.
|
|
|
|
## Create a new work package
|
|
|
|
To get started, create a new work package in your project, [open the project](../projects/#open-an-existing-project) with the project drop-down menu, navigate to the **module work packages** in the project menu.
|
|
|
|
Within the work packages module, click the green + Create button to create a new work package. In the drop down menu, choose which type of work package you want to create, e.g. a task or a milestone.
|
|
|
|
![create-work-package](create-work-package-1569611257373.png)
|
|
|
|
A split screen view is opened with the new work package form on the right and the list of already existing work packages on the left.
|
|
|
|
If there are not yet any work packages in the project, you will see a message that there are no work packages to be displayed in the list.
|
|
|
|
In the empty form on the right, you can enter all relevant information for this work package, e.g. the subject and a description, set an assignee, a due date or any other field. The fields you can populate are called **work package attributes**. Also, you can add attachments with copy & paste or with drag and drop.
|
|
|
|
Click the green **Save** button to create the work package.
|
|
|
|
![split-screen-work-packages](split-screen-work-packages.png)
|
|
|
|
The work package will the be displayed in the list view:
|
|
|
|
![list-view-work-package](1569611758166.png)
|
|
|
|
Another option to create a work package is to do it from the header menu. The [work package types](../../user-guide/projects/project-settings/work-package-types/#work-package-types) that are activated, will be shown and you can select the relevant work package type to be created.
|
|
|
|
![create-work-package-header](create-work-package-header.png)
|
|
|
|
Once you click on the work package type that you want to create, the work package detail view opens and you have to **select the project** that you want to create the work package for.
|
|
|
|
![create-work-package-define-project](create-work-package-define-project.png)
|
|
|
|
Then you follow the same steps as mentioned above to fill in the your work package attributes and save it.
|
|
|
|
## Open and edit a work package
|
|
|
|
To open and edit an existing work package from the list, select the work package in the list which you want to edit and click on the **open details view** icon in the work package list or on top of the list to open the split screen view. Other ways to open it would be to double-click on the work package or to click on the work package ID.
|
|
|
|
![open-details-view-work-packages](open-details-view-work-packages.png)
|
|
|
|
By clicking through the list on the left hand side you will see the details of each work package on the right in the split screen.
|
|
|
|
Click in any of the fields to **update a work package**, e.g. description. Click the checkmark at the bottom of the input field to save changes.
|
|
|
|
![edit-work-package](1569612205009.png)
|
|
|
|
To **update the status**, click on the highlighted displayed status on top of the form and select the new status from the drop-down.
|
|
|
|
![update-status](1569612428626.png)
|
|
|
|
## Activity of work packages
|
|
|
|
To keep informed about all changes to a work package, open the **ACTIVITY** tab in the details view.
|
|
|
|
Here you will see all changes which have been made to this work package.
|
|
|
|
You can also insert a comment at the end of the Activity list.
|
|
|
|
![activity-work-packages](activity-work-packages.png)
|
|
|
|
The aggregation of changes in the Activity list can be configured in the [system administration](../../system-admin-guide/system-settings/display-settings/#time-and-date-formatting-aggregation-of-changes-in-activity).
|
|
|
|
To find out more about the work package functionalities, please visit our detailed [user guide for work packages](../../user-guide/work-packages).
|
|
|
|
|