@ -37,7 +37,7 @@ describe 'date inplace editor', |
|
|
|
|
with_settings: { date_format: '%Y-%m-%d' }, |
|
|
|
|
js: true, selenium: true do |
|
|
|
|
let(:project) { create :project_with_types, public: true } |
|
|
|
|
let(:work_package) { create :work_package, project: project, start_date: '2016-01-01' } |
|
|
|
|
let(:work_package) { create :work_package, project: project, start_date: '2016-01-02' } |
|
|
|
|
let(:user) { create :admin } |
|
|
|
|
let(:work_packages_page) { Pages::FullWorkPackage.new(work_package, project) } |
|
|
|
|
let(:wp_table) { Pages::WorkPackagesTable.new(project) } |
|
|
|
@ -61,7 +61,20 @@ describe 'date inplace editor', |
|
|
|
|
|
|
|
|
|
start_date.save! |
|
|
|
|
start_date.expect_inactive! |
|
|
|
|
start_date.expect_state_text '2016-01-01 - 2016-01-25' |
|
|
|
|
start_date.expect_state_text '2016-01-02 - 2016-01-25' |
|
|
|
|
end |
|
|
|
|
|
|
|
|
|
it 'reverses the dates if the selected date is before the current start date' do |
|
|
|
|
start_date.activate! |
|
|
|
|
start_date.expect_active! |
|
|
|
|
|
|
|
|
|
start_date.datepicker.expect_year '2016' |
|
|
|
|
start_date.datepicker.expect_month 'January', true |
|
|
|
|
start_date.datepicker.select_day '1' |
|
|
|
|
|
|
|
|
|
start_date.save! |
|
|
|
|
start_date.expect_inactive! |
|
|
|
|
start_date.expect_state_text '2016-01-01 - 2016-01-02' |
|
|
|
|
end |
|
|
|
|
|
|
|
|
|
it 'can set "today" as a date via the provided link' do |
|
|
|
@ -79,6 +92,69 @@ describe 'date inplace editor', |
|
|
|
|
start_date.expect_state_text "#{Time.zone.today.strftime('%Y-%m-%d')} - no finish date" |
|
|
|
|
end |
|
|
|
|
|
|
|
|
|
context 'with start and end date set' do |
|
|
|
|
let(:work_package) { create :work_package, project: project, start_date: '2016-01-02', due_date: '2016-01-25' } |
|
|
|
|
|
|
|
|
|
it 'selecting a date before the current start date will change the start date' do |
|
|
|
|
start_date.activate! |
|
|
|
|
start_date.expect_active! |
|
|
|
|
|
|
|
|
|
start_date.datepicker.expect_year '2016' |
|
|
|
|
start_date.datepicker.expect_month 'January', true |
|
|
|
|
start_date.datepicker.select_day '1' |
|
|
|
|
|
|
|
|
|
start_date.save! |
|
|
|
|
start_date.expect_inactive! |
|
|
|
|
start_date.expect_state_text '2016-01-01 - 2016-01-25' |
|
|
|
|
end |
|
|
|
|
|
|
|
|
|
it 'selecting a date in between changes the date that is currently in focus' do |
|
|
|
|
start_date.activate! |
|
|
|
|
start_date.expect_active! |
|
|
|
|
|
|
|
|
|
start_date.datepicker.expect_year '2016' |
|
|
|
|
start_date.datepicker.expect_month 'January', true |
|
|
|
|
start_date.datepicker.select_day '3' |
|
|
|
|
|
|
|
|
|
# Since the focus shifts automatically, we can directly click again to modify the end date |
|
|
|
|
start_date.datepicker.select_day '21' |
|
|
|
|
|
|
|
|
|
start_date.save! |
|
|
|
|
start_date.expect_inactive! |
|
|
|
|
start_date.expect_state_text '2016-01-03 - 2016-01-21' |
|
|
|
|
end |
|
|
|
|
|
|
|
|
|
it 'selecting a date after the current finish date will change either start or finish depending on the focus' do |
|
|
|
|
start_date.activate! |
|
|
|
|
start_date.expect_active! |
|
|
|
|
|
|
|
|
|
start_date.datepicker.expect_year '2016' |
|
|
|
|
start_date.datepicker.expect_month 'January', true |
|
|
|
|
|
|
|
|
|
# Focus the end date field |
|
|
|
|
start_date.activate_due_date_within_modal |
|
|
|
|
start_date.datepicker.set_date '2016-03-01', true |
|
|
|
|
|
|
|
|
|
# Since the end date is focused, the date will become the new end date |
|
|
|
|
start_date.save! |
|
|
|
|
start_date.expect_inactive! |
|
|
|
|
start_date.expect_state_text '2016-01-02 - 2016-03-01' |
|
|
|
|
|
|
|
|
|
# Activating again and now changing the start date to something after the current end date |
|
|
|
|
start_date.activate! |
|
|
|
|
start_date.expect_active! |
|
|
|
|
|
|
|
|
|
start_date.datepicker.expect_year '2016' |
|
|
|
|
start_date.datepicker.expect_month 'January', true |
|
|
|
|
start_date.datepicker.set_date '2016-04-01', true |
|
|
|
|
|
|
|
|
|
# This will set the new start and unset the end date |
|
|
|
|
start_date.save! |
|
|
|
|
start_date.expect_inactive! |
|
|
|
|
start_date.expect_state_text '2016-04-01 - no finish date' |
|
|
|
|
end |
|
|
|
|
end |
|
|
|
|
|
|
|
|
|
context 'with the start date empty' do |
|
|
|
|
let(:work_package) { create :work_package, project: project, start_date: nil } |
|
|
|
|
|
|
|
|
|